Vineyard Wind 1

Vineyard Wind 1 Lease Area Map
Vineyard Wind 1 Lease Area

What’s New?

On July 13, 2024, Vineyard Wind 1’s installed blade at Wind Turbine Generator (WTG) AW-38 failed, resulting in the release of blade debris into the environment. Emergency notifications and measures, including emergency consultations with state and federal agencies, were activated to contain and retrieve the released debris.  

The Bureau of Safety and Environmental Enforcement (BSEE) exercised its oversight authority and suspended further blade installation and power production until certain conditions were met. A root-cause analysis of the blade failure was conducted by the manufacturer and installer (GE Vernova), which found that the failure was due to a manufacturing deviation.  

BOEM requested that the lessee submit a revised Construction and Operations Plan (COP) to BOEM. Vineyard Wind 1 submitted a COP revision addendum for BOEM’s review on Dec. 5, 2024, which describes the activities that would be involved with removing the blades installed on up to 22 wind turbine generators before the July 13, 2024, blade failure.  

On Jan.17, 2025, BOEM completed its review and approved Vineyard Wind 1’s COP revision. On the same day, BSEE lifted its suspension order.

The documents for this COP revision are available below:

Background

In May 2021, the Departments of the Interior and Commerce announced the approval of the construction and operation of the first large-scale, offshore wind project in the United States, located offshore Massachusetts. The 800-megawatt Vineyard Wind 1 Offshore Wind Energy Project will be located approximately 12 nautical miles offshore Martha's Vineyard and 12 nautical miles offshore Nantucket in the northern portion of Vineyard Wind’s lease area (OCS-A 0501).

Record of Decision Supplements from the U.S. Army Corps of Engineers